The Martin Finance Committee discussed multiple TLM projects at their monthly meeting this week.
The first project has been in the works since October of 2019 and would have put sidewalks from Elm Street to University and Lee Streets.
Interim Mayor David Belote said the city has paid a total of almost 87,000 on this project.
The second project has cost the city over $98,000 with about $25,000 remaining…
The Committee voted to halt both projects.